hospital room, constructed by Broadmoor, LLC

Ochsner Emergency COVID Buildout

Ochsner Emergency COVID Buildout

Client: Ochsner Health Systems
Location: Jefferson, LA
Architect: Rozas Ward Architects
Date of Completion: July 2020

In just 103 days, under the stress and uncertainty of the COVID-19 pandemic, Broadmoor maintained the health and safety of the whole team throughout the completion of 102 new ICU beds, 90,000 square feet of 3 floors on top of an existing and active Ochsner hospital tower. Our team overcame many logistical and scheduling challenges to create a safe environment for the people suffering at this time. To finish this project within 3 months of mobilizing, Broadmoor bypassed the typical 10-12-week lead times for material procurement for everything from flooring to doors that had to meet hospital and fire code and provide design continuity for the hospital. These challenges and unique project requirements that Broadmoor overcame serve as a testament as to how we Honorably Serve Our Communities.